| Detailed Project Statuses: |
Engineer(s): Sam Ritter, Clyde Bazile, Kevin Albertson
2020-07-10: Updating target date to 2020-07-24 (14 weeks)
- Pushing out by two weeks for consistency, however the team estimates this should complete by July 17.
- We expect all tickets that are not in progress or in review to be trivial efforts
- Clyde was back in office this week, so we have been able to once again devote some full attention to this.
- After completing the last ticket in the C 4.4 epic, Kevin will be able to focus in here as well.
- With Sam's schedule in flux, we are planning to pull as much of this work into the core team as possible to ensure it is wrapped up ASAP.
2020-06-26: Updating target date to 2020-07-10 (12 weeks)
- Most of the remaining work is just going to be tests, and we expect that some of the scheduled tickets will be handled by the other in-flight work in this epic.
- Staffing is going to be a bit light right now - Clyde is OOO next week, so Kevin will plan to focus on CXX for 4.4 and Sam will plan to focus on CXX FLE work.
- Takeaway: seem to be right on track for July 10.
2020-06-18: Updating target date to 2020-07-03 (11 Weeks)
- 12 Tickets outstanding: 3 in Code Review, 1 In Progress, 1 Investigating, 6 Scheduled, 1 Blocked
- C team members continuing to contribute to C++ work.
- Closed out 5 tickets:
CXX-1868, CXX-1951, CXX-1994, CXX-2005, CXX-2010
- PgM Believes there is some risk of hitting 7/8 GA date, already mitigating as much as possible by having C team focus on CXX.
2020-06-05: Updating target date to 2020-06-19 (9 Weeks)
- Reevaluated remaining work in our team meeting today, after assessing capacity we believe June 19th is the most accurate estimate of our completion date
- C team members continuing to work on remaining C++ work
- Will plan to release a Beta, not RC, for .Live
2020-05-29: Updating target date to 2020-06-09 (8 Weeks, -3 days)
- Updating date by unusual increment to align with our targeted beta/RC release for .Live
- C team members pivoting to this work today. Will first focus on closing smaller tickets so we can better evaluate the remaining substantial work.
2020-05-15: On track for 2020-06-12
- Continuing to work on FLE and BSON related FLE work.
- BSON in code review, don't expect unpleasant surprises or refactors.
- BSON was the last remaining blocker.
- FLE should take another week or two.
- Will add additional engineers if necessary to get CXX 4.4 out the door.
- Rather finish CXX support for 4.4 than test planned maintenance due to release timeline.
- Test planned maintenance would become top priority following 4.4 work.
2020-05-01: Updating target date to 2020-06-12 (8 Weeks)
- Not much progress on this project with focus on FLE.
- This pushes the date beyond the GA date for 4.4.
- Once C 4.4 support wraps, we plan to have the team redirect to this project to pull this date back in.
2020-04-17: Setting initial target date of 2020-05-29 (6 Weeks)
- Work starting alongside FLE, focusing on API changes first.
|