Uploaded image for project: 'C Driver'
  1. C Driver
  2. CDRIVER-2915

Build libmongocrypt library

    • Hide

      2019-01-07: Initial target of 2019-02-04 (4 weeks)

      • Kevin to review the tickets and confirm the timeline.

      2019-02-04: Updated target 2019-03-04 (8 weeks)

      • Spec is still in flux.

      2019-03-04: Updated target 2018-04-29 (12 weeks)

      2019-04-01: Updated target of 2019-05-13 (14 weeks)

      2019-04-29: updated target date of 2019-05-27 (16 weeks)

      • 3.5 tickets per week and down to 12 tickets in project.
      • So 2 weeks is just too optimistic, especially if any more tickets get filed.

      2019-05-27: updated target date of 2019-06-24 (20 weeks)

      • Aiming to fully unblock other drivers by end of next week.
        • With part of the caching work and API change in review.
      • Interns arrive next week.
      • We now have 19 tickets left.

      2019-06-24: Updated target of 2019-07-08 (22 weeks)

      2019-07-19 : Updated target date 2019-08-05 (26weeks)
      Tickets should be wrapped up by 07-26 but adding the two week increment.

      Scope of this epic kept growing, we have decided to take a few tickets out as they are follow up tasks and proceeding to close this epic.

      Show
      2019-01-07: Initial target of 2019-02-04 (4 weeks) Kevin to review the tickets and confirm the timeline. 2019-02-04: Updated target 2019-03-04 (8 weeks) Spec is still in flux. 2019-03-04: Updated target 2018-04-29 (12 weeks) For detailed project breakdown see releases page : https://jira.mongodb.org/projects/CDRIVER?selectedItem=com.atlassian.jira.jira-projects-plugin%3Arelease-page&status=unreleased 2019-04-01: Updated target of 2019-05-13 (14 weeks) 2019-04-29: updated target date of 2019-05-27 (16 weeks) 3.5 tickets per week and down to 12 tickets in project. So 2 weeks is just too optimistic, especially if any more tickets get filed. 2019-05-27: updated target date of 2019-06-24 (20 weeks) Aiming to fully unblock other drivers by end of next week. With part of the caching work and API change in review. Interns arrive next week. We now have 19 tickets left. 2019-06-24: Updated target of 2019-07-08 (22 weeks) 2019-07-19 : Updated target date 2019-08-05 (26weeks) Tickets should be wrapped up by 07-26 but adding the two week increment. Scope of this epic kept growing, we have decided to take a few tickets out as they are follow up tasks and proceeding to close this epic.

      For all necessary work the C/C++ driver team is doing for building the libmongocrypt library that the rest driver can wrap.

            Assignee:
            kevin.albertson@mongodb.com Kevin Albertson
            Reporter:
            kevin.albertson@mongodb.com Kevin Albertson
            Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

              Created:
              Updated:
              Resolved:
              31 weeks, 1 day