Engineer(s): Sam Ritter, Clyde Bazile, Kevin Albertson
2020-07-10: Updating target date to 2020-07-24 (14 weeks)
- Pushing out by two weeks for consistency, however the team estimates this should complete by July 17.
- Prose tests are in review and waiting on some minor tweaks from Sam, but bulk of the work is done.
- Corpus tests are the last remaining substantial work.
- Removed
CXX-1855 as we are still planning on not blocking this epic for the tutorial work, that can be completed after release.
- With Sam's schedule in flux, we are planning to pull as much of this work into the core team as possible to ensure it is wrapped up ASAP.
- Since Clyde is nearly wrapped up with the CXX 4.4 epic, we would like him to pick up
CXX-2018: Corpus testing for BSON values, and since Kevin is nearly wrapped up with the C 4.4 epic, we would like him to take point on CXX-2022.
2020-06-26: Updating target date to 2020-07-10 (12 weeks)
- We expect the remaining tickets to be fairly small other than
CXX-2022: Implement FLE Corpus Tests, which might take a bit more lifting. Planning for Kevin to address CXX-2022 due to his involvement in the corpus tests for C - we anticipate this effort will take a day or two.
- We are prioritizing the tests over
CXX-1855: Create Language Specific FLE Tutorials as we believe the tutorials should not block us from releasing and should not require a release in order to be updated.
- Takeaway: Similar to CXX for 4.4 epic, this seems to be right on track for July 10.
2020-06-18: Updating target date to 2020-07-03 (11 Weeks)
-6 Tickets outstanding: 1 in Code Review, 1 In Progress, 2 Scheduled, 2 Open
-C team members continuing to contribute to C++ work.
-Closed out 2 tickets: CXX-1687, CXX-1972
2020-05-29: Updating target end date to 2020-06-09 (7.5 weeks)
- Updating date by unusual increment to align with our targeted beta/RC release for .Live
- Fairly close to completion, should just be additional testing from here on out.
- Unclear how valuable additional tests would be, we may end up deciding to forego some prose tests.
2020-05-15: Updating target end date to 2020-05-29 (6 weeks)
- BSON was the last remaining blocker, FLE should take another week or two.
- Will add additional engineers if necessary to get CXX 4.4 out the door.
2020-05-01: Updating target end date by 2020-05-15 (4 weeks)
- Work on b_type struct to bson_value_t conversions has been more complex than initially expected.
- This will be the priority once Sam returns from vacation next week.
2020-04-17: Setting initial target date of 2020-05-08 (3 Weeks)
- Auto encryption has been merged.
- Working with Drew to move forward with explicit encryption work.
2020-04-03:
- Will provide target end date in one week, pending input on Sam's schedule.
- Nearly complete with work to have BSON own its own memory. Working with Drew on code review.
- Next will work on explicit encryption.