      2019-02-04: initial target of 2019-04-15 (10 weeks)

      • Aiming for design complete by Feb 18.
      • 2 months of calendar time from there (very tentative, pending design).
      • This date is also "API complete" for BIC.

      2019-02-18: updated target of 2019-05-13 (14 weeks)

      • Last 2 weeks were blocked on GA.
      • Probably 2 more weeks of being blocked on GA+vacation.

      2019-04-01: no change.

      • Wrap prototype and make tickets by end of next week.

      2019-04-29: updated target of 2019-05-27 (16 weeks)

      • BI connector should still be unblocked as of 05-13.

      2019-05-13: no change

      • But now aiming to unblock BI Connector by 05-17.

      2019-05-27: updated target of 2019-06-24 (20 weeks)

      • 3 person-weeks of work divided by 3 engineers. Doubled for caution.

      2019-06-24: updated target of 2019-07-08 (22 weeks)

      • MongoDB World and optimistic estimation.
      Show
      2019-02-04: initial target of 2019-04-15 (10 weeks) Aiming for design complete by Feb 18. 2 months of calendar time from there (very tentative, pending design). This date is also "API complete" for BIC. 2019-02-18: updated target of 2019-05-13 (14 weeks) Last 2 weeks were blocked on GA. Probably 2 more weeks of being blocked on GA+vacation. 2019-04-01: no change. Wrap prototype and make tickets by end of next week. 2019-04-29: updated target of 2019-05-27 (16 weeks) BI connector should still be unblocked as of 05-13. 2019-05-13: no change But now aiming to unblock BI Connector by 05-17. 2019-05-27: updated target of 2019-06-24 (20 weeks) 3 person-weeks of work divided by 3 engineers. Doubled for caution. 2019-06-24: updated target of 2019-07-08 (22 weeks) MongoDB World and optimistic estimation.

      Description

      Scope, Design, and Implement an improved Driver Library.

        Attachments

          Issue Links

            Activity

              People

              Assignee:
              kris.brandow Kristofer Brandow (Inactive)
              Reporter:
              kris.brandow Kristofer Brandow (Inactive)
              Participants:
              Votes:
              0 Vote for this issue
              Watchers:
              2 Start watching this issue

                Dates

                Created:
                Updated:
                Resolved:
                Start date:
                End date: