Uploaded image for project: 'PHP Driver: Library'
  1. PHP Driver: Library
  2. PHPLIB-683

Run Test Suites Against Serverless in Evergreen

    • Type: Icon: Epic Epic
    • Resolution: Fixed
    • Priority: Icon: Major - P3 Major - P3
    • 1.12.0
    • Affects Version/s: None
    • Component/s: Spec Comp
    • Labels:
      None
    • 2
    • 4
    • 4
    • 100
    • Hide

      Summary: This epic captures the effort of testing the PHP driver against the serverless proxy.

      Engineer(s): Jeremy Mikola
      2020-10-21: Updating target date to 2021-10-29

      • This is nearly complete and just pending the addition of load balanced serverless connectivity tests.
      • Jeremy is planning to wrap this work while Andreas is out. It is currently third in our scheduled queue with only two small bugs ahead of it.

      Engineer(s): Andreas Braun
      2020-10-06: Updating target date to 2021-10-29

      • This is nearly complete and just pending the addition of load balanced serverless connectivity tests.
      • Andreas is on leave and will have this at the top of his engineering list when he returns, though management duties are consuming the majority of his time.

      Engineer(s): Andreas Braun
      2020-09-23: Updating target date to 2021-10-29

      • This is nearly complete and just pending the addition of connectivity tests.
      • Andreas is on leave this week and will have this at the top of his engineering list when he returns, though management duties are consuming the majority of his time.

      Engineer(s): Andreas Braun
      2020-08-25: Updating target date to 2021-09-03

      • This had been on hold while Andreas was tending to management duties surrounding 5.0 releases, QP planning, and performance and growth cycle.
      • Andreas aimed to finish this ahead of his PTO, however we ran out of time for reviewing - the team will resume when he returns on Aug 30th.

      Engineer(s): Andreas Braun
      2020-08-11: Keeping target date of 2021-08-13

      • This had been on hold while Andreas was tending to management duties surrounding 5.0 releases, QP planning, and performance and growth cycle.
      • Andreas has picked this back up this week and has the work in code review, targeting completion by the end of the week.

      Engineer(s): Andreas Braun
      2020-07-28: Setting target date to 2021-08-13

      • This has generally been on hold while Andreas has been attending to management duties surrounding 5.0 releases, QP planning, and performance and growth cycle.
      • There is still some work to be done on the C side before this can be fully completed by PHP, which Andreas also has in flight.

      Engineer(s): Andreas Braun
      Cost in Eng Weeks: 2 Original | 1 To Date | 2 Est Final
      2020-07-14: Setting target date to 2021-07-30

      • Andreas has been chipping away at the PHP effort as he is able to while simultaneously working through the serverless testing issues in C, which should in turn progress the PHP work.
      • Andreas has had to split his focus to coordinate releases on his team.
      Show
      Summary: This epic captures the effort of testing the PHP driver against the serverless proxy. Engineer(s): Jeremy Mikola 2020-10-21: Updating target date to 2021-10-29 This is nearly complete and just pending the addition of load balanced serverless connectivity tests. Jeremy is planning to wrap this work while Andreas is out. It is currently third in our scheduled queue with only two small bugs ahead of it. Engineer(s): Andreas Braun 2020-10-06: Updating target date to 2021-10-29 This is nearly complete and just pending the addition of load balanced serverless connectivity tests. Andreas is on leave and will have this at the top of his engineering list when he returns, though management duties are consuming the majority of his time. Engineer(s): Andreas Braun 2020-09-23: Updating target date to 2021-10-29 This is nearly complete and just pending the addition of connectivity tests. Andreas is on leave this week and will have this at the top of his engineering list when he returns, though management duties are consuming the majority of his time. Engineer(s): Andreas Braun 2020-08-25: Updating target date to 2021-09-03 This had been on hold while Andreas was tending to management duties surrounding 5.0 releases, QP planning, and performance and growth cycle. Andreas aimed to finish this ahead of his PTO, however we ran out of time for reviewing - the team will resume when he returns on Aug 30th. Engineer(s): Andreas Braun 2020-08-11: Keeping target date of 2021-08-13 This had been on hold while Andreas was tending to management duties surrounding 5.0 releases, QP planning, and performance and growth cycle. Andreas has picked this back up this week and has the work in code review, targeting completion by the end of the week. Engineer(s): Andreas Braun 2020-07-28: Setting target date to 2021-08-13 This has generally been on hold while Andreas has been attending to management duties surrounding 5.0 releases, QP planning, and performance and growth cycle. There is still some work to be done on the C side before this can be fully completed by PHP, which Andreas also has in flight. Engineer(s): Andreas Braun Cost in Eng Weeks: 2 Original | 1 To Date | 2 Est Final 2020-07-14: Setting target date to 2021-07-30 Andreas has been chipping away at the PHP effort as he is able to while simultaneously working through the serverless testing issues in C, which should in turn progress the PHP work. Andreas has had to split his focus to coordinate releases on his team.

      Run a subset of specification tests against Serverless.

            Assignee:
            jmikola@mongodb.com Jeremy Mikola
            Reporter:
            backlog-server-pm Backlog - Core Eng Program Management Team
            Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

              Created:
              Updated:
              Resolved:
              17 weeks, 1 day