2018-09-13 : Initial target ?
POC in progress, can provide estimate for project completion only after POC is completed.
2018-09-27 : Target 2018-10-26 (4weeks)
Estimate based on POC.
2018-10-11 : Updated target 2018-11-09 (6weeks)
Design is still in progress
2018-11-08 : Updated target 2018-12-07 (10weeks)
Design is complete and the API has been finalized. The work has started and is estimated to take 4 weeks with all code changes and review.
2018-12-06 : Work has stalled because of spec and POC work plus Prashant is on vacation. Bernie to provide updated estimate next week.
2019-01-17 : No update to timeline. Python is planning to do some performance testing before proceeding further.
2019-01-31 : 2019-02-22
Still working on performance testing. Now have a realistic load scenario. Adding 4 week estimate as this will be a priority for Q1 after the spec change ticket assigned to Prashant.
2019-02-14 : epic on hold until spec changes are done.
2019-02-28 : Updated target 2019-03-15
Adding two weeks. This work has been restarted and the plan is to do a release mid-march with the user requested feature.
2019-03-14: Updated target 2019-03-29 (+2weeks)
Spent time working on beta, deferred work on this project. Harder than we thought.
2019-04-01: updated target of 2019-04-15 (?? weeks)
- Design doc for final bits in flight.
- Should be just 2 more for design+impl.
2019-04-15: updated target of 2019-04-29 (?? weeks)
- In CR now, hoping to push in next day or two based on feedback.