Uploaded image for project: 'Python Driver'
  1. Python Driver
  2. PYTHON-4561

Async PyMongo Full Release

    • Type: Icon: Epic Epic
    • Resolution: Unresolved
    • Priority: Icon: Unknown Unknown
    • None
    • Affects Version/s: None
    • Component/s: None
    • None
    • Python Drivers
    • Hide
      1. What would you like to communicate to the user about this feature?
      2. Would you like the user to see examples of the syntax and/or executable code and its output?
      3. Which versions of the driver/connector does this apply to?
      Show
      1. What would you like to communicate to the user about this feature? 2. Would you like the user to see examples of the syntax and/or executable code and its output? 3. Which versions of the driver/connector does this apply to?
    • To Do
    • Async PyMongo Production Release
    • 26
    • 5
    • 26
    • 100
    • Hide

      Engineer(s): XX

      YYYY-MM-DD: Target date set to / on track for / updated to YYYY-MM-DD

      • Rational for any project delays/change in end date, if applicable
      • Known risks or blockers:
        •  
      • Completed over the last 2 weeks:
        •  
      • Focus over the next 2 weeks
        •  
      • Anything else to share?

      Engineer(s): Noah Stapp

      2024-11-25

      • What was completed over the last two weeks?
        • Discovered async SDAM cancellation bug while converting test suite to async.
        • Investigating and resolving async SDAM cancellation bug.
      • What's the focus over the next two weeks?
        • Re-evaluating the technical design of async pymongo to produce a new technical design that addresses the problems discovered during implementation.
      • Impediments encountered over the last two weeks?
        • Async SDAM has revealed significant deficiencies in Python's asyncio implementation requiring us to revisit our original design.

      Engineer(s): Noah Stapp

      2024-11-11

      • What was completed over the last two weeks?
        • Work on hold for Spec Fest + greenerbuild rotation.
      • What's the focus over the next two weeks?
        • Continue conversion of test suites to async.
      • Impediments encountered over the last two weeks?
        • N/A

      Engineer(s): Noah Stapp

      2024-10-25

      • What was completed over the last two weeks?
        • Continued work to finish the conversion of test suites to async
        • Continued debugging of failing async tests
      • What's the focus over the next two weeks?
        • Not being worked on due to Spec Fest and Greenerbuild rotation.
      • Impediments encountered over the last two weeks?
        • Async test failures are difficult to debug due to the concurrent nature of coroutine execution.

      Engineer(s): Noah Stapp, Iris Ho

      2024-10-11

      • What was completed over the last two weeks?
        • Continued work to finish the conversion of test suites to async
        • Started work on SDAM using tasks instead of threads
      • Converted unified test runner to async
      • What's the focus over the next two weeks?
        • Finishing the SDAM work
        • Continue test suite conversion
      Show
      Engineer(s): XX YYYY-MM-DD : Target date set to / on track for / updated to YYYY-MM-DD Rational for any project delays/change in end date, if applicable Known risks or blockers:   Completed over the last 2 weeks:   Focus over the next 2 weeks   Anything else to share? Engineer(s): Noah Stapp 2024-11-25 What was completed over the last two weeks? Discovered async SDAM cancellation bug while converting test suite to async. Investigating and resolving async SDAM cancellation bug. What's the focus over the next two weeks? Re-evaluating the technical design of async pymongo to produce a new technical design that addresses the problems discovered during implementation. Impediments encountered over the last two weeks? Async SDAM has revealed significant deficiencies in Python's asyncio implementation requiring us to revisit our original design. Engineer(s): Noah Stapp 2024-11-11 What was completed over the last two weeks? Work on hold for Spec Fest + greenerbuild rotation. What's the focus over the next two weeks? Continue conversion of test suites to async. Impediments encountered over the last two weeks? N/A Engineer(s): Noah Stapp 2024-10-25 What was completed over the last two weeks? Continued work to finish the conversion of test suites to async Continued debugging of failing async tests What's the focus over the next two weeks? Not being worked on due to Spec Fest and Greenerbuild rotation. Impediments encountered over the last two weeks? Async test failures are difficult to debug due to the concurrent nature of coroutine execution. Engineer(s): Noah Stapp, Iris Ho 2024-10-11 What was completed over the last two weeks? Continued work to finish the conversion of test suites to async Started work on SDAM using tasks instead of threads Converted unified test runner to async What's the focus over the next two weeks? Finishing the SDAM work Continue test suite conversion

      Summary

      What is the problem or use case, what are we trying to achieve?

      Motivation

      Who is the affected end user?

      Who are the stakeholders?

      How does this affect the end user?

      Are they blocked? Are they annoyed? Are they confused?

      How likely is it that this problem or use case will occur?

      Main path? Edge case?

      If the problem does occur, what are the consequences and how severe are they?

      Minor annoyance at a log message? Performance concern? Outage/unavailability? Failover can't complete?

      Is this issue urgent?

      Does this ticket have a required timeline? What is it?

      Is this ticket required by a downstream team?

      Needed by e.g. Atlas, Shell, Compass?

      Is this ticket only for tests?

      Is this ticket have any functional impact, or is it just test improvements?

      Cast of Characters

      Engineering Lead:
      Document Author:
      POCers:
      Product Owner:
      Program Manager:
      Stakeholders:

      Channels & Docs

      Slack Channel

      [Scope Document|some.url]

      [Technical Design Document|some.url]

            Assignee:
            noah.stapp@mongodb.com Noah Stapp
            Reporter:
            noah.stapp@mongodb.com Noah Stapp
            Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

              Created:
              Updated:
              26 weeks