Fix workgen to run checkpoint thread in parallel with other threads

XMLWordPrintableJSON

    • Type: Bug
    • Resolution: Unresolved
    • Priority: Major - P3
    • None
    • Affects Version/s: None
    • Component/s: Not Applicable
    • Storage Engines, Storage Engines - Transactions
    • SE Transactions - 2025-06-06
    • 5
    • 0

      As part of a workload design a checkpoint thread is scheduled at the end of the workload run.
      The scope of this ticket is to schedule checkpoint thread also along with other threads instead of at the end of the workload run.